Proposed Schedule

Week #01

-Make final edits to animatic, production design and art direction.
-Shoot high speed/stop motion photography for Shot #06
-See if the above step worked correctly. If it didn't, shoot again during Week #02.
-Assemble cut-outs necessary for Shot #04 and Shot #10.


Week #02

-Take individual frames for Shot #06 into Illustrator for augmentation. Composite everything together in After Effects. See if it works.*
-Animate cut-outs designed during Week #01.

* This is contingent upon the shots taken during Week #01 working correctly. If they do not, everything will be pushed back by 1 week.


Week #03-Week #06

-2D rough animate the rest of the film using Flash.


Week #07-Week #10

-Clean up Flash animation.
-Composite stop motion animations with 2D.
-Fix what didn't work right the first time.


Week #11-Week #20

-Further enhance the whole piece.